October 15, 2026
Crews started tearing down Cedar Hall in September. It is one of the last large buildings on the 280-acre former Tinley Park Mental Health Center campus at 7400-7600 W. 183rd St. That puts the Tinley Park-Park District close to finishing Phase Two of the cleanup it calls Remediate 280. Once the last buildings are gone, the view from Harlem Avenue will look like a finished job. It isn't one. The step that decides when the land can be redeveloped is a soil and groundwater investigation scheduled to start in mid-October 2026. You won't see much of it from the road, and its results go to the Illinois Environmental Protection Agency measured against recreational-use standards.
That investigation sets the timeline. It also sets the standard every future plan for these 280 acres starts from.
The campus closed for good in July 2012. When the environmental firm Tetra Tech inspected it in September 2023, in a survey reported that October, it counted 47 buildings plus a network of underground tunnels. Most of the halls were named for trees: Willow, Pine, Oak, Hickory, Sycamore, Maple, Spruce, Mimosa and Cedar. The grounds also held a power plant, administration buildings, neighborhood houses and seven cottages.
The Park District bought the property from the State of Illinois for $1. The sale closed in February 2024, and at the time the District announced $15 million in state cleanup money. Phase One cleared overgrowth, removed underground storage tanks, put up perimeter fencing, and tore down most of the buildings. Phase Two is paid for by another $18 million state grant, so the state has put $33 million into the work. The District's September 2026 newsletter says every phase is funded entirely by state grants.
Here is the District's own building-by-building status, from its September committee presentation:
| Structure | Status |
|---|---|
| Water Tower, Building 19 | Removed over the summer |
| Power plant, Building 20 | Removed, foundation removal underway |
| Oak Hall, Building 4 | Foundation and dock removal, backfilling next |
| Willow Hall, Building 5 | Active demolition of a large footprint |
| Cedar Hall, Building 23 | Demolition permit to begin September 21 |
| Tunnels | Most removed, concrete being processed on site |
Brandenburg Industrial Service Co. is the demolition contractor. Its crews have been clearing more than 5,600 linear feet of underground tunnels, while True North Consultants monitors dust around the site.
With the buildings gone, the work moves underground. The District has enrolled the property in the IEPA's Site Remediation Program. It filed separate investigation plans for three parts of the campus so that each can move as fast as possible:
The plans were revised after IEPA comments, working with the consultant Tetra Tech. They call for more than 1,000 borings across the 280 acres, often with soil samples taken at several depths in each one, plus groundwater, sediment and surface water sampling wherever crews find water.
The District has laid out the schedule from here:
The mid-October start is a forecast. The District has not given a date for the final letter. Two small pieces are already finished: the IEPA has issued No Further Remediation letters for two areas that used to hold underground storage tanks.
Recreational-use clearance is a cleanup benchmark. It is not an adopted land-use plan. Still, it lines up with the only concept the owner has published. In December 2022, while bidding on the property, the Park District released a first phase covering 90 acres next to its Freedom Park. That phase included multipurpose athletic fields, a domed complex with a full-size soccer field, a stadium with a track, a playground and splash pad designed for people with special needs, concessions and spectator stands, lighting, parking, a pond, picnic areas and open green space. The release pitched the complex as a draw for neighboring communities and a source of revenue for the District.
The Village of Tinley Park had pushed a different idea. In March 2023, before the District took ownership, the Village described a mixed-use project for the 280 acres with sports and ice facilities, entertainment, apartments and townhomes, a trail and expanded wetlands, as reported by Patch. That concept came out while the Village was trying to acquire the land. The Park District owns it now.
Today, the District's property page presents the 2022 ideas as earlier thinking and makes no final commitment:
"We look forward to engaging with the community for ideas to redevelop the land once we begin the redevelopment process. We have previously released our ideas for the first 90 acres of the property."
Our research found no revised concept from 2025 or 2026, no scheduled public input session, and no public statement on what final approvals the land will need or what role the Village will play. The order of events is clear, though. The redevelopment process can't start until the No Further Remediation letter arrives, and the District has said community input comes once that process begins. So the borings starting this month come before any public conversation about fields, domes or anything else.
A large indoor sports building may open before any part of the 280 acres does. At 7600 W. 191st St., eight numbered streets south of the campus, GK Development LLC is listed by the Village as the developer of a 42-acre project built around a 142,000-square-foot dome. Severe winds knocked the dome down on July 27, before it had opened, Patch reported. The owners said they were assessing the damage and working to restore it.
The Village's current projects page, updated in September 2026, still shows the dome opening in November and its restaurant in December. Both dates are projections. The Interstate Sports Dome describes baseball, softball and pickleball, six multipurpose fields, 14 batting cages, six pickleball courts, and a bar and grill called TK's Clubhouse. Its online calendar already offers pickleball court and batting cage reservations for the week of October 5. That shows bookings are open, not that the building is.
This is a private project. It is separate from the Park District's 2022 idea for a domed soccer complex on the old campus. But it means south Tinley Park may get indoor fields this winter, while the public land to the north is still waiting on lab results.
The District publishes Remediate 280 updates in a few places:
The next update worth watching for is confirmation that drilling crews are out on the 90-acre parcel and the two other investigation areas. After that, the next big milestone is the IEPA's comprehensive No Further Remediation letter.
Large projects like this one tend to come up when neighbors talk about what's changing near home. If you have questions about the 183rd Street site and what it could mean for your corner of Tinley Park, Carla Gorman follows this project closely and is happy to talk it through. Let's Connect.
Stay up to date on the latest real estate trends.
My experience and dedication allows my clients to achieve their goals in the shortest amount of time with the highest investment. Whether you are a first-time home buyer or a seasoned seller, I will bring energy, experience, and integrity to your next real estate venture. Contact me today to begin your real estate experience!