October 22, 2026
"Construction is expected to begin on the new tennis courts in the coming weeks."
That line is from the Lemont Park District's May 1, 2026 community update. Almost six months later, the District's own October progress report says the tennis permits have been submitted and the project goes to bid this month. The District now expects it to be finished in late summer 2027.
During the same months, the two buildings that looked hardest to keep running stayed open while crews worked inside them. Centennial Community Center's preschool wing is complete. The CORE's addition is in structural framing and foundation work. The 2024 referendum's building work is tracking the spring plan, while its outdoor projects have moved into 2027. If you use the 127th Street campus, that order decides what this winter looks like and when the parking and court changes reach you.
The District published one update in May and another in October. Side by side, they show where things moved and where they stalled.
| Project | What the May 1 update said | What the October 2026 update says |
|---|---|---|
| Centennial Community Center | First phase covers the north preschool and south corridors. Preschool to return in fall | Preschool complete. Construction continues throughout the building |
| The CORE | First phase is an addition on the east side. East lot closed from May 18 until "later this Fall" | Structural framing and foundation underway |
| Tennis and pickleball on 127th Street | Tennis construction to begin "in the coming weeks" | Permits submitted. Bids in mid-October, accepted in November. Completion late summer 2027 |
| Derby Farms Park | Construction expected to start later this year | Bids in mid-October. Site clearing possibly later this year. Construction starts spring 2027, completion late summer 2027 |
Both building projects are following the phased plan the District described in the spring. Both outdoor projects have moved back by at least a season. The October page also says its renderings "may change based on budgets and bids." That makes the bid round now underway the first real test of the outdoor plans.
Centennial Community Center at 16028 127th Street is still busy and still a construction site. According to the October report, the gym will keep hosting classes and programs in the evening, with limited hours during the day. The report also asks visitors to "make note of new entrances." It doesn't say which doors changed, so check the project update page before your first winter visit, especially if you're dropping off for a class.
One change is permanent. The racquetball courts went offline after May 15. The District cited limited use, shifting interests, and accessibility, and it plans to use the space for other needs in the building.
The District says the building has served the community for more than 30 years. When the renovation is done, it's supposed to have:
The Centennial work has a projected budget of $6.9 million and an anticipated completion window of 2026 to 2028. One sign of how far along it is came on the Park District's August 25 board agenda, which included a proposed approval of up to $220,000 for furniture and fixtures at Centennial and The CORE. Boards don't usually take up furniture until the rooms are coming into view.
The CORE Fitness & Aquatic Complex at 16050 127th Street is operating during construction. Its facility page lists hours of 5 a.m. to 9 p.m. on weekdays and 7 a.m. to 5 p.m. on weekends. It also posts current lap swim, aquatics, and fitness class schedules and notes that they can change.
The construction you can see is on the building's east side, where the first-phase addition is going up. The $2.0 million project adds fitness studios, rearranges the layout, and enlarges the lobby. Like Centennial, it has an anticipated completion window of 2026 to 2028.
Parking is the detail early-morning regulars have been working around. The May update said the east lot would close on May 18 and "not reopen until later this Fall." Patch reported the same timeline when construction began. The October report doesn't mention the lot, so treat the reopening as unannounced until the District posts it.
The court project is the piece that ties the campus together. The May update describes a two-part plan:
The extra Centennial parking comes with the court work. So while the CORE's east lot is out and Centennial's entrances are shifting, the parking relief arrives with the project expected to finish in late summer 2027. The courts carry a projected budget of $2.5 million.
The public bid listing gives the courts a 16050 127th Street address and sets the bid deadline for October 28 at 1 p.m. CDT. The District expects to accept bids in November.
Derby Farms Park at 13950 131st Street is on the same bid deadline as the courts. The District hopes to start clearing the site later this year, begin construction in spring 2027, and finish in late summer 2027. The $4.6 million plan includes:
The traffic signal is the infrastructure piece neighbors near the intersection will want to follow. Patch reported in June 2025 that the Village approved a design engineering agreement with HR Green, capped at $54,606.51, for a signal at 131st Street and Derby Road. The county recommended the signal because of the traffic the park is expected to bring. As of the October update, Cook County and the Village of Lemont "continue to work on the approved traffic signal." No completion date has been published.
The next milestones are close together, and the first two land within a week of this post:
The money behind all of this dates to March 2024, when 70% of voters approved the referendum. The District is paying for it by reissuing bonds after its existing bonds matured in 2025, which keeps the tax levy where it was. The May release put the total construction budget at about $17 million. The four project estimates on the October page add up to $16.0 million. The November bid results will be the first contract figures for the two outdoor projects that slipped.
If you're planning a move in Lemont and want to know how the Park District's timeline at Derby Farms or along 127th Street fits your own dates, Carla Gorman is happy to go through it with you. Let's Connect.
Stay up to date on the latest real estate trends.
My experience and dedication allows my clients to achieve their goals in the shortest amount of time with the highest investment. Whether you are a first-time home buyer or a seasoned seller, I will bring energy, experience, and integrity to your next real estate venture. Contact me today to begin your real estate experience!